Prokhorivskyi kvartal construction progress: update log

FAKTOR team
Share:

This is a single living page about the construction progress of Prokhorivskyi kvartal at 40 Prokhorovska Street. New figures are added to the update log at the bottom rather than published as separate news items, so the whole construction history for this address stays in one place.

The description of the complex, the layouts and current offers are on the main page: Prokhorivskyi kvartal.

Where construction stands now

The quarter consists of seven buildings split into fifteen sections, and the sections run in different phases. As of October 2026 the picture is this: sections 1.1-1.4 were completed back in the fourth quarter of 2021, sections 2.1-2.2 and 3.1-3.4 were commissioned between 2023 and 2025, sections 4.1-4.2 are at facade work with a deadline of the fourth quarter of 2026, and sections 5.1-5.2 and 6.1 are having their walls built with a deadline of the third quarter of 2027.

The housing class is comfort, the buildings are sixteen storeys, the walls are aerated concrete block with mineral wool insulation, heating comes from an own boiler house and parking is underground. The developer is Stikon.

What that means for a buyer

At one address apartments in completed sections and square metres still under construction are on sale at the same time. The difference is not only the price but what you are buying: in a completed section it is a finished property with registered title, in one under construction it is a deadline and the risk attached to that deadline.

So the first question about this quarter is always the same: which section a particular apartment belongs to. Two apartments with the same layout can sit in sections six years apart in completion.

Update log

10.10.2026. According to dom.ria.com sections 4.1-4.2 are at facade work with a deadline of the fourth quarter of 2026. Sections 5.1-5.2 and 6.1 are at wall construction with a deadline of the third quarter of 2027. Sections 2.x and 3.x are in operation. LUN lists buildings of fifteen to eighteen storeys in the quarter and confirms the own boiler house, the underground parking and a generator in the buildings.

What is nearby

Gymnasium No 18 is two hundred metres away, listed in the state register of educational institutions as Odesa Gymnasium No 18. A kindergarten is three hundred metres away and a supermarket two hundred and eighty. Mykhailivska Square is 270 metres away and Prokhorovskyi park nine hundred. The Privoz market is one and a half kilometres away, 2,1 kilometres and four minutes by road. Dumska Square is about three kilometres away, 4,3 kilometres and seven minutes by road.

When will the last sections of Prokhorivskyi kvartal be completed?

The deadline for sections 5.1-5.2 and 6.1 is the third quarter of 2027 according to dom.ria.com.

Which sections are already finished?

Sections 1.1-1.4 were completed in the fourth quarter of 2021, and sections 2.1-2.2 and 3.1-3.4 were commissioned between 2023 and 2025.

What stage are sections 4.1 and 4.2 at?

Facade work, with a deadline of the fourth quarter of 2026.

Who is the developer?

The Stikon company.

How many storeys do the buildings have?

Sixteen. LUN lists fifteen to eighteen for individual buildings, so the height is worth checking by section.

Is this page updated?

Yes, new figures are added to the update log on this same page with the real date.

What is available in the finished and in the future sections of Prokhorivskyi kvartal can be reviewed with a FAKTOR specialist.

Looking for an apartment in Odesa?

We will shortlist options for your budget and guide the deal from the first viewing to signing.

FAKTOR team
Real estate agency: sales, new developments, rentals and legal support of deals in Odesa.
All articles
New listings on Telegram New properties daily, no spam

For sale now: 11 398 We are online